Detail NR1 ELEC/INST RM/KL/CM
2024-10-18
443-PH1-3RD-FLOOR
Wahyu Adi Triono
Problem: Air lancing observation activation
Action:
Check at side found there are air supply and cable power. Check at I/O panel 4th floor cable is ready. Advise install panel for relay at beside panel I/O 4C1-2RB-75 ( JAJAT & ADI )

Status: done